Preliminary grid connection analysis and solution for WPP ST3-1/2 Visoka Zelovo

Abstract

The study deals with and selects the method of connecting the wind power plant ST3-1/2 Visoka Zelovo to the 110 kV transmission network or the 30 kV distribution network, and examines power flows in characteristic stationary modes of operation, in variants of complete availability of the transmission network and variants N-1